|
|
Jamie Sturgess
VP Projects and Environment
Rosemont Copper Company
4500 Cherry Creek South Drive
Suite 1040
Denver, CO 80246
Dear Mr. Sturgess:
As you know, the Coronado National Forest has been working with specialists
in the Southwest Region and with specialists outside the agency to complete
a thorough review of the Rosemont Mine Plan of Operations (MPO). Our review
focused on whether or not the MPO contained the level of information sufficient
to demonstrate preliminary project feasibility and to allow the Forest
to initiate and complete the scoping phase of National Environmental Policy
Act (NEPA) analysis and support data collection decisions. The review
process followed in part the guidelines presented in Appendix C of the
“Training Guide for Reclamation Bond Estimation and Administration
for Mineral Plans of Operation authorized and administered under 36 CFR
228A, USDA – Forest Service, April, 2004".

The following is a list of the documents (proposed Plan and supporting
documents) which were provided to us for this review:
Augusta Resource Corporation
Rosemont Project
Mine
Plan
of Operations, July 11, 2007
Electrical
Power Supply and Water Supply Supplement, July 25, 2007
Tetra Tech
Reclamation and Closure Plan,
July, 2007
Survey of Salvage
Topsoil Resources, June 2007
Storage Area Soil Salvage Estimates,
June, 2007
Operational Areas Soil Salvage
Estimates, June, 2007
Baseline Geochemical
Characterization, June, 2007
Dry Tailings Facility Design,
June, 2007
Geologic Hazards Assessment, June,
2007
Geotechnical Study, June, 2007
Leaching Facilities
Design, June, 2007
Site Water Management Plan,
June, 2007
Waste Management Plan, June, 2007
Technical Memorandum: Viewshed Analysis,
June 29, 2007
Tetra Tech and Errol L. Montgomery & Associates, Inc.
Vector Colorado, LLC
Technical Memorandums:
Geology
& Seismotectonic Review Rosemont Mine Sighting Study, April 20, 2007
Preliminary
Trip Report and Phase 1 Sampling & Analysis Plan, July 26, 2006
Sighting
Study - Pond Sizing Memorandum, June 2, 2006
Rosemount
Tailings Sighting Study - May 26, 2006
WLR_Consulting, Inc.
Wardrop
Washington Group International
Generally, we found that the MPO provided a sufficient level of information
to determine what site specific environmental engineering and environmental
baseline data will be necessary to support analysis of alternatives and
prediction of effects. A significant exception is the description provided
in the MPO and other documents we reviewed relative to ground and surface
water resources.
|
|


|
For the ground and surface water portions of the MPO, there needs
to be a description of the potential for mine dewatering, potential for
a post mining pit lake with the geochemical characteristics that could
be expected, and a water balance plan describing all water sources and
uses, including groundwater withdrawals in the area of the mine site itself.
There is sufficient information provided for the west side of the project
area for the CAP water, pipeline routes, production wells, etc., but very
little groundwater information is included on the mine site itself.
|
|
|
|
The following specific information is needed concerning water in and
around the project area:
|
|
 |
General information on the location of any dewatering wells. This information
would probably be based on local geology and what is currently known of
the groundwater regime, and locations may change as the project develops.
|
|
 |
A conceptual groundwater model based on current information. This model
will be recalibrated regularly, probably annually, for the first few years,
and will be utilized for estimating impacts to ground and surface water
in the vicinity.
|
|
 |
A conceptual groundwater monitoring plan. There should be at least four
or five wells just outside the ultimate pit perimeter before any mine
operations begin. Recording of water levels should begin well before any
mine operations commence, and the recording interval should be no greater
than one week. There should be some wells installed at greater distances
for monitoring the growth of the cone of depression, four or five to begin
with, and plans for more to monitor the horizontal growth of the drawdown.
Both shallow and deep aquifers should be targeted.
|
|
 |
All pertinent information on groundwater wells installed for this project,
including drill logs, completion logs, screened interval locations and
depths, sample intervals, completion depths, materials used in well development,
water flow rates, and water quality data.
|
|
 |
Information on existing groundwater levels, direction of flow, gradient,
transmissivity and pump testing.
|
|
 |
|
|
 |
Vertical characterization of groundwater quality, including characterization
of different geologic units at different depths, such as fractures, alluvial
subflow, and alluvial aquifers.
|
|
 |
Data on existing stream channels and banks, including profile information,
cross sections bankfull discharge, pebble count, width to depth ratio,
and sinuosity; this is especially important at the Point of Compliance
dam area where the project will outfall to the undisturbed stream.
|
|
 |
Data on existing spring characterization, including location, quantity,
flow volumes, and water quality, and information on potential spring upwelling
under project features such as the leach pad liner.
|
|
 |
Information on sampling protocols, analytical methods, quality assurance
and quality control methods for each type of hydrologic and hydrogeologic
data collected.
|
|
 |
Design of retention ponds in the area of the waste rock pile. Currently
the MPO calls for a 100 foot horizontal setback from the hydrologic grade
break to the base of the toe. It appears that the storm water will percolate
back into the waste rock pile; what is the design freeboard prior to overtopping
into an adjacent drainage such as Oak Tree Canyon?
|
|
| |
The following information is needed in order to clarify questions about
land status in the project area, and to improve the readability of maps
and diagrams in the MPO and support documents:
|
|
 |
Clarification on what is meant by “controlled by Augusta Resource Corporation"
(Executive Summary, page 1, third paragraph).
|
|
 |
Clarification as to the number of unpatented claims there are associated
with this project. Paragraph 2 of section 1.2 lists 850 unpatented claims,
while Appendix A lists 864. In addition to BLM serial numbers, the list
of unpatented claims should include claimant information, township range
and section, and type of claim.
|
|
 |
Identification of ownership (private, county, state, and federal) administrative
status (proclaimed Forest boundary, Las Cienegas National Conservation
Area, Santa Rita Experimental Range, etc), and management (Forest Service,
BLM, University of Arizona, State Land Department, etc.) on all project
maps and diagrams.
|
|
 |
Section, township and range lines on whatever is being portrayed (ancillary
facilities, general site arrangements, geology, etc.) on a map or diagram,
regardless of scale (from less than an acre to several townships). Maps
should have a connection to on the ground features or references; currently
many of the maps use only digital elevation model data which is difficult
to relate to real world locations.
|
|
 |
Different colors for each ownership or managerial jurisdiction shown on
project maps and diagrams. I suggest utilizing the ownership colors used
on Forest Service ˝" – 1 mile Forest visitor maps. The proclaimed National
Forest Boundary should be portrayed on maps as a bold black line.
|
|
 |
A definition, in common terms, of the phrase “Rosemont Land Position".
Does this equate to the area including al unpatented mining claims and
private land held by the corporation?
|
|
 |
A map showing the individual unpatented lode mining claims in relationship
to the private ownership and National Forest system lands.
|
|
 |
A depiction of project study boundary limits (i.e., project footprint)
on all project related maps, regardless of scale.
|
|
| |
Other information that is needed with the MPO and supporting documents
includes the following:
|
|
 |
The state in which Augusta Resource Corporation was incorporated and the
articles of incorporation.
|
|
 |
Identification of staging areas and temporary roads needed for the preproduction
phase (Figure 2.2 of the MPO).
|
|
 |
Information relative to hazardous material quantities and their specific
storage locations.
|
|
 |
Initial designs for the Waste Rock Facility.
|
|
 |
Details on procedures to be implemented in the event of a temporary shut-down
in operations.
|
|
 |
A description of the disposition of existing mine workings.
|
|
| |
Once Augusta resource Corporation has provided the Forest with the information
requested in this letter, along with the changes to the MPO, agency specialists
will review the submissions and determine whether thee information is
sufficient for initiating the Notice of Intent.
As you continue to provide the Coronado National Forest (and the Forest
Service in general) with project related documents, I ask that you advise
us as to what information you consider confidential or proprietary.
Sincerely,
JEANINE DERBY
Forest Supervisor
Cc: Mark E Schwab, Michael A Linden
|
|